Current Project
We are in the process of finishing out a Wesmac
50 hull to yacht standards with an expected launch date of Spring
2007. The boat arrived at our facility in the Spring of
2005 as a bare hull.
Completed items as of Spring 2006:
- Added Nacelles to the Hull for the Jets
- Installed Fuel Tanks and Systems
- Installed Engines and Jets
- Installed Following Systems: A/C, Water, Watermaker, Waste & Holding Tanks / Pumps, Washer / Dryer, Central Drainage, Espar,
Thruster, Generator, Muffler, Bow Roller Assembly
- Construct & Fair Cabin House
- Construct Salon Sole
- Construct Interior Partitions Below
- Aft Cockpit Gridwork
- Engine Insulation
Still to do:
- Finish Cockpit / Lockers
- Put on Winterback
- Install Windows & Hatches
- Build Cabin Interior, Cabinetry
- Install Headliners
- Install Galley
- Basic Wiring and Plumbing
- Install Electronics and Steering System
- Awlgrip Top to Bottom
- Finish Interior Woodwork
Feel free to stop by our facility on Route 90 in Rockland
Maine to tour the Progress...
Please click on any picture below for a closer look:
 |
 |
 |
| Wesmac
50 Hull arriving at Johanson Boatworks Spring 2005 |
Backing
Wesmac 50 into the Work Bay |
Forming
a Mold for the Cabin House on the Wesmac 50 |
 |
 |
 |
| Melamine
Installed and Form Ready for Laminating |
Cabin
House Lamination Complete and Ready for Fairing |
Bolting Down the Engines
on the Wesmac 50 |
 |
 |
 |
| Grid Work for Cockpit
Sole Wesmac 50 |
A/C, Water, Plumbing,
Misc. Systems in the Fuel Room |
Interior Partitions and
Shower Sump in Wesmac 50 |
 |
 |
 |
| Interior
modifications |
Fairing
inside |
Final
fair on helm station |
 |
 |
 |
| Passenger
seat |
Galley
construction |
Forward
end galley and passenger seat |
 |
 |
 |
| Aft
end of galley area |
Guest
cabin bunktop |
Guest
cabin |
 |
 |
 |
| Queen
forward berth |
Head
cabinet construction |
Shower
stall |
 |
 |
 |
| Face
frame for head cabinet |
Head
vanity and cabinet |
Washer/dryer
install |
 |
 |
 |
| Air
conditioning and watermaker |
Engine
room insulation |
Paint
out propane locker |
 |
 |
 |
| Final
fairing on cabin house |
Bowsprit
layout |
Tape
off for spray |
 |
 |
 |
| Mask
off for cabin side spray |
Prep
for spray |
Prep
for spray |
 |
 |
 |
| Masking
off for spray |
Fairing
waterline |
Tape
waterline |
 |
 |
 |
| Finish
coat topsides |
Stage
topsides |
Hull
awlgripped/prep deck |
 |
 |
 |
| Teak
rubrails |
Forming
radius forward bunk |
Doors
ready for finishing |
 |
 |
 |
| Prefinished
doors and cabinetry |
Finished
forward bunk tops |
Prime
air handlers |
 |
|
|
| Fabricating
pieces |
|
|
|